We are now in the eighth week of construction and are making good progress. The dry wall is almost complete and the HVAC system is about 80% complete waiting for the ERV units to arrive. The fire alarm system and the data and phone cables are in place and Comporium has made the connection to the building. The kennel gates have been installed and all of the walls in the building have been insulated. The exterior of the building, where the overhead doors were, has been finished to match the rest of the building. The exhaust system ducting for the clothes dryers and bathrooms have been installed.