We have just completed ten weeks of construction and are making great progress. The additional lighting in the kennel has been installed and the fiberglass panels around the perimeter of that area is being installed today. The dry wall installation is complete and there is prime paint on all of the walls. The ceiling grid has been installed and the florescent lights and air outlets and returns have been installed. We will begin installing the ceiling tiles with insulation next week after the county inspects the above ceiling work. The material is already in the building. The ERV units have been installed and the HVAC system is up and running. The outside outlets, lights and water faucet are also complete. We are still on schedule to have the occupancy permit by the first week of September so that we will have several weeks to move into the new facility.